CS605 Assignment 3 Solution Spring 2017

Alpha Company is a software house currently working on a project of Hotel management system. Alpha Company has to complete this project in 30 days. Draw the Task network diagram for Alpha Company to complete this project, the information about each task is given below:

Name of Task Description of Task Duration in days Immediate Predecessor
Requirement Specification 4
Design 6 A
Code 10 B
Test 6 C
Document 4 D, C

Question No. 2

Quality Soft is a software house currently working on a project of stock management system. For this project they have calculated the Cost performance index (CPI) = 0.9, the Actual cost work performed (ACWP) is 550. You are required to find the Budgeted Cost of Work Perform (BCWP).

Provide your answer in the following table:

CPI=BCWP/ACWP

0.9=BCWP/550

0.9*550=BCWP

BCWP=495